Clear standard operating procedures (SOPs) are essential to making shore power connections reliable, Henrik Gram Rasmussen, Senior Maritime Electrical Engineer at Maersk Line, and head of Maersk’s fleet-wide shore power retrofit programme, told the Shore Power Summit 2026 in Rotterdam.
“One of the main things that we see these days is the missing or unclear SOPs, which sometimes restricts us from actually connecting. Even if the port is ready and the vessel is ready, we can still fail to connect,” he said, stressing that clear communication, coordination and agreed procedures between ship and shore teams were key to making connections “successful and safe”. Rasmussen said the process of developing procedures was often too slow, urging the industry to step up their efforts.
But having procedures in place is only part of the challenge. Shore power connections can still be disrupted by late information-sharing between ship and shore teams, language barriers and insufficiently trained personnel. And when something goes wrong, establishing where the fault originated is not always straightforward.
Maersk is seeing an increasing need for failure investigations and root-cause analysis when connections fail or have to be aborted. However, Henrik said the industry lacked a common platform for sharing lessons learned from such incidents, making it harder to use operational experience to improve connection reliability.
He also pointed to the absence of synchronised time logs and event reports, which makes it difficult to establish what happened during a failed connection and whether the problem originated on the vessel or shore side. A shared operating picture would help the parties involved understand incidents and accelerate recovery.
Even with preparations in place, the operating environment can introduce further complications. Bunkering and the movement of personnel and spare parts can interfere with cable deployment and connection operations, while weather conditions, such as hurricanes at US ports and typhoons in China, can impose safety restrictions. Berth positioning can also complicate the connection process.
Rasmussen also highlighted cases in which cargo-handling equipment had mistakenly lifted and damaged vessels’ AMP container units, putting them out of service. In such cases, repairs are often difficult to complete before the next port call.
Looking ahead, Rasmusen said ports must factor future vessel requirements into shore-side infrastructure plans, including charging facilities for hybrid and fully electric ships. The rapid development of battery-powered container shipping, exemplified by China’s 740-TEU Ningyuan Diankun, the world’s largest fully electric seagoing container ship, and Eitzen Group’s plans for two 900-TEU battery-electric feeder vessels, underlines the need for ports to anticipate growing demand for high-capacity charging infrastructure.
Maersk launched its shore power retrofit programme in 2021, initially targeting vessels operating on US and Chinese routes in response to regulatory requirements, while also preparing the fleet for greater flexibility as shore power requirements evolved. The programme covers the company’s owned fleet, which accounts for roughly half of its more than 700 owned and chartered vessels. The subsequent introduction of the EU’s Fit for 55 package, which set a 2030 compliance deadline, prompted Maersk to expand its retrofit plans into a wider roadmap covering 240 vessels.
Working with suppliers, Maersk developed a standardised low-power container solution that can be transferred between vessels as trading patterns change. The vessel-side infrastructure required to accommodate the system, however, must be installed during the five-year special periodic survey (SPS), as this work cannot be carried out while a vessel is in operation.
The programme is now around 80% complete, with the focus shifting from installations to activating vessels already prepared for shore power. By October, 202 vessels had been retrofitted, of which 149 were active and 59 inactive, with 36 vessels activated to date. Around 10% of the fleet may not be retrofitted, as those vessels are expected to leave service before the investment becomes necessary.