Shore Power Summit: Port of Bilbao ramping up its OPS network

The Port of Bilbao is taking on this task with BilbOPS, a 30 MW shore power network with 11 connection points across seven berths. The first phase of the project was completed in May 2026.

Jasmina Ovcina Mandra·November 19, 2026·7 min
Back to Marasi News
Shore Power Summit: Port of Bilbao ramping up its OPS network

For ports investing in onshore power supply (OPS), installing the infrastructure is only part of the challenge. Grid capacity, vessel compatibility and electricity prices all determine whether shore power can become a commercially sustainable service.

The Port of Bilbao is taking on this task with BilbOPS, a 30 MW shore power network with 11 connection points across seven berths. The first phase of the project was completed in May 2026, while the remaining infrastructure is scheduled for ­commissioning in December 2027 and full operational deployment in ­February 2028.

The network could serve more than 900 vessel calls annually. However, the port acknowledges that predicting actual electricity demand remains a big challenge in developing the project.

The first phase of BilbOPS comprises two 2.5 MVA connection points for Ro-Ro and Ro-Pax vessels. The systems are operational but currently undergoing maintenance while awaiting the completion of vessel retrofits needed for OPS connections, Igor Martín Calvo, Head of Renewable Energy at Bilbao Port Authority, told WorldCargo News.

The €50.1 million second phase, now under construction, will add nine connection points. Five will serve container ships, four rated at up to 2.5 MVA and one at up to 7.5 MVA, while the remaining points will accommodate Ro-Ro, Ro-Pax and cruise vessels. Each connection is designed to have mobile cable management systems (CMS) allowing ships from different operators to use the facilities.

The first phase was awarded to ­Tecuni under a €4.7 million design, construction and maintenance contract, while the second phase is being delivered by a joint venture comprising Sampol Ingeniería y Obras, Comsa Instalaciones y Sistemas Industriales and Montajes Eléctricos San Ignacio. Equipment suppliers include Ingeteam, Ormazabal, Schneider, AVEVA, igus and Debusman.

The works are being carried out while Bilbao continues handling commercial shipping traffic, requiring close co-ordination between the port authority, terminal operators and contractors. The port authority co-ordinates weekly construction plans with terminal operators and has phased work to keep facilities operational. The main practical challenges vary, the port said, ranging from civil works to finding suitable locations for electrical and cable management equipment within existing terminals.

Bilbao described demand for vessel electricity as a “big unknown”, given that most ships are not yet equipped for OPS. Calvo expects cruise ships to lead adoption, as many already have the necessary equipment installed and the sector is further advanced in environmental awareness.

“As for shipping companies, there is currently a call for EU funding to support vessel retrofits, which helps. But at present, shipping companies in general still have a lot of work to do in this respect,” Calvo said.

To adequately size its OPS systems, the port is designing the infrastructure to be scalable and expandable if future demand exceeds initial projections. Sizing each installation has required detailed modelling, drawing on shipping line data, databases and operational estimates. The port has analysed historical vessel calls, traffic forecasts, shipping service patterns and the time available to supply power after connection and disconnection procedures. These estimates have been compared with actual consumption data from other ports with operational OPS systems to test how theoretical demand translates into real-world use.

“Ultimately, the economic viability of OPS depends not only on the duration of individual port calls, but also on achieving sufficient and predictable infrastructure utilisation over time,” Calvo said.

When BilbOPS was first planned, the existing electricity distribution network could not meet the additional demand, requiring a 60 MVA expansion of Iberdrola’s Santurtzi substation. Substation works are still ongoing, with energisation scheduled for January 2027. The investment includes three distribution centres, 11 transformer centres and 20 flexible power outlets across the berths. The network also incorporates a 7.3 km powertrack and a 1.34 km subsea cable supplying the cruise berths.

“Physically bringing power to the port area is proving far from easy,” Calvo added, citing environmental restrictions on overhead power lines and the technical complexity of installing underground cables in land reclaimed from the sea.

The port has co-ordinated its OPS rollout with renewable-energy generation from the outset. It is deploying four photovoltaic installations with a combined peak capacity of around 4.25 MWp under an €11.5 million contract, alongside a separate €2.9 million investment in rooftop solar. In addition, the port has a 10 MW wind farm at Punta Lucero, operated by Energías Renovables del Abra since 2006, and is exploring a 1 MW wave-energy prototype with the potential for a larger installation of up to 12 MW.

Bilbao is financing the €78.7 million ­BilbOPS project through EU grants and its own resources. In October 2022, it won a €14.2 million grant under the EU’s Connecting Europe Facility (CEF) Transport programme. The port also secured an €80 million EIB loan in 2024, part of which will finance the second phase of the project.

The port plans to recover part of the cost of providing the service through OPS tariffs charged to shipping companies. “The Port Authority is ­proactively working on a pricing framework aimed at ensuring that the service is competitive, reasonable and transparent for shipping companies, while contributing to its long-term economic sustainability,” Calvo said.

The port says OPS will be integrated into its vessel call procedures. Ships will need to request OPS through the European Maritime Single Window when submitting port calls, so electricity supply can be planned ­alongside vessel arrivals and berthing operations.

Vessels using OPS will be eligible for a 50% reduction in the vessel port fee, subject to the applicable conditions, Calvo added, with the aim to further incentivise OPS uptake.

Moving forward, the port is considering energy storage and electricity-sharing arrangements with terminals and industrial users to increase renewable electricity use, reduce grid dependence and limit exposure to price fluctuations. Calvo pointed out that having a good Power Management System (PMS) integrated into the microgrid “helps a great deal.”

“Looking ahead, the economic sustainability of OPS will depend on achieving sufficient and predictable vessel utilisation, maintaining competitive electricity prices and ensuring efficient energy procurement and operation,“ Calvo said.

The port considers regulatory stability equally important to the investment case. The EU’s Alternative Fuels Infrastructure Regulation (AFIR) and FuelEU Maritime framework provide the fundamental framework for the rollout of OPS infrastructure. Ports need confidence that the rules and their core decarbonisation objectives will remain stable and predictable, Calvo pointed out.

While practical experience may justify targeted adjustments, any regulatory review should safeguard existing investments and encourage further OPS expansion, he said.

Looking back on the development of BilbOPS, the port believes that the communication and control infrastructure needed greater attention during project planning. Furthermore, there is a need to plan for the period between completion of the port infrastructure and the point at which vessels are required to connect. “Every port has its own particularities,” Calvo said, “but ensuring that ports and shipping lines are ready to make the transition is a lesson that applies across the sector,” he concluded.

Debusman, a Spanish provider of electrical and mechanical equipment, has supplied a mobile CMS for the Port of Bilbao’s OPS installation at the A5 Ro-Ro berths. The battery-powered system serves two connection points, driving between a storage garage and the quay to connect vessels to OPS. A cable-protection system allows the CMS to move up to 40m after connection while protecting the cable from damage. Commissioning and operator training were completed in June 2026. The company is due to supply a second Ro-Ro CMS and cable-protection system to Bilbao by the end of 2026 as part of the second phase of the project, along with a shore-power socket-box system for the cruise berth.

Debusman has also supplied a mobile Ro-Ro CMS and dual-connection socket box at the Port of Vigo, with commissioning scheduled for November 2026. In 2025, the company supplied six dual-connector OPS systems for container vessels at the Port of Alicante. Fixed-boom shore connection systems are also under development for the ports of Tarifa and Algeciras, with two units going to each port in 2027.