Türkiye’s Asyaport is undertaking an expansion programme to increase its annual handling capacity from 2.5m to 4m TEU. The terminal is adding cranes and electric terminal tractors while expanding its use of shore power.
Located in Tekirdağ, on the Sea of Marmara, Asyaport is a joint venture between MSC-linked Terminal Investment Limited (TiL) and the Turkish Soyuer family. It began operations in July 2015 and serves mainly as a transhipment hub connecting the Black Sea, Aegean and Mediterranean. Its hinterland connections are supported by MSC logistics subsidiary MEDLOG, which operates its own truck fleet, two nearby container storage facilities and a local rail terminal. A new road also links the port to the railway station, bypassing Tekirdağ’s urban centre.
During a media visit on 9 November, Buse Dölarslan, Senior Strategy and Business Development Specialist at Asyaport, outlined recent investments and future development plans. The terminal handled 2.21m TEU in 2025, up 5.5% from 2.10m TEU in 2024. Throughput reached 1.86m TEU in the first ten months of 2026, putting the terminal on course for another annual record.
The expansion includes a 400m quay extension, scheduled for completion by the end of this year. Once completed, it will allow the port to accommodate three ultra-large container vessels simultaneously. Asyaport commissioned four STS cranes in October and two RTGs in July, bringing its fleet to 15 STS cranes and 32 RTGs.
The terminal’s masterplan also includes provision for further yard expansion.
Asyaport became Türkiye’s first container terminal to offer shore power in October 2024, when MSC Oscar connected to its new onshore power supply (OPS) system. The 8 MVA installation can supply up to seven vessels simultaneously. According to Asyaport, the system has supplied 10m kWh of electricity to 182 vessels, avoiding an estimated 6,000t of CO2 emissions.
The terminal is also pursuing a US$10m programme to introduce 100 electric terminal tractors. Four entered service in early 2026, with a further 30 scheduled for deployment in December. The terminal currently operates 75 LNG-powered tractors alongside the four electric units.
Its renewable energy installations include 3,020 solar panels with a combined installed capacity of 1,289 kW. The panels generate approximately 1.3m kWh annually.
***A more detailed report on Asyaport’s operations, investments, equipment and future development plans will appear in the December print issue of WorldCargo News.